The Good Faith Exception to Fraudulent Liens
Florida’s lien law specifically prohibits a lienor from improperly increasing the amount of its lien beyond the amount owed or including amounts for work not performed. See Section 713.31, Florida Statutes. The lien law even imposes penalties against a lienor for recording such a "fraudulent lien." At the same time, however, the lien law provides that a lien will not be found "fraudulent" if the lienor’s actions in recording it were in good faith. It is important for a lienor to be aware, though, that "good faith" will only go so far in avoiding a finding that its lien is fraudulent. The lien that a consultant recorded against Mr. and Mrs. Medellin’s home provides an example of how good faith will not always prevent a court from finding a lien is fraudulent. Medellin v. MLA Consulting, Inc., 69 So. 3d 372 (Fla. 5th DCA 2011). While the trial court found that the consultant’s lien was not fraudulent, because the consultant believed in good faith that the amount was due, the appellate court disagreed. The appellate court clarified the good faith exception to be limited to preventing a lien from being deemed fraudulent when the issue is whether the amount included in the lien was due, and there was a good faith dispute over whether it was due. The appellate court found that the Medellins’ consultant’s good faith was irrelevant because the issue was whether the amount included in the consultant’s lien was for work that entitled the consultant to record a lien against the Medellins’ house. Because the work underlying the disputed amount in the consultant’s lien was not lienable, the appellate court found that the consultant’s lien was fraudulent. With the Medellin court’s holding, it is now even more important that a lienor be sure the amounts it is including in its lien are for work that will properly support a lien.
The general rule is that bid protests must be timely filed in order to be considered. Most government agencies in Florida have specific deadlines for which a bid protest must be filed. These deadlines are expressed in terms of days, or even hours, and may specify the exact method that the protest or notice of protest must be submitted to be considered timely filed. A Protest filed after the deadline is usually considered a waiver of the protestor’s rights.
It’s no secret that cash is tight these days and unfortunately that translates into payment problems on many jobs, including high-profile public projects. Don’t fall into the trap of overconfidence in your ability to get paid based solely on history or good relations with your customers. Owners, contractors and subcontractors alike are all feeling the pinch of reduced work, higher collateral requirements for bonding and rising insurance costs, just to name a few. That customer with whom you’ve worked well for years may be experiencing serious cash problems of which you aren’t aware, leaving you to hold the bag if you haven’t properly perfected your claims while on the job.
I wanted to address key terms for any contruction contract. Although some of these may seem mind numbingly obvious, I have seen contracts over the years that failed to address very critical points.
As often happens on construction projects, disputes arise between the contracting parties. One party may claim they have not been paid. The other party may claim the work has not been done or was improperly done. What happens when the parties are unable to amicably resolve their differences and their contract has an arbitration clause? Must the parties arbitrate their dispute or can their dispute be decided in a court of law?
How do you monitor a public agency's review and evaluation of bids and proposals? What right do you have to observe evaluation committees when proposals are evaluated? The answers to these questions provide assistance to bidders who want to actively monitor the award process.
A recent Fourth District Court of Appeal Case, Florida Hurricane Protection and Awning Company, Inc. v. Pastina, shows the importance of defining the scope of a prevailing party attorneys’ fee provision in contracts. In Pastina, the attorneys’ fee provision in the contract allowed for the contractor to recover its attorneys’ fees when the contractor had to sue for collection of any amounts owed. There was no mention of any situation where the owner could recover fees. Subsequently, a dispute arose between the parties and the owner prevailed at trial and sought to recover his attorneys’ fees. The trial court held that under